Table 7 Operating cost for absorption chiller cooling system

From: Energy efficiency and greenhouse gas emission abatement opportunities for an existing gas treatment plant: a comprehensive technical and economic analysis

Item

Value

Unit

AHU #1 fan energy consumption

222,807

kWh/year

AHU #2 fan energy consumption

21,628

kWh/year

AHU #3 fan energy consumption

12,977

kWh/year

Chilled water pump

526,680

kWh/year

Condenser water pump

588,924

kWh/year

Total additional energy consumption

1,373,016

kWh/year

Equivalent input energy for energy production

29,014

MMBtu/year

Total cost for extra energy required

138,000

US$/year

Additional GHG emissions

1540

Ton CO2-eq/year