From: Preparation of inorganic catalysts from ceramic industry wastes for use in the production of biofuel
Cost | US $ | |
---|---|---|
Installation | 0.45 PCE | 181,575 |
Piping | 0.45 PCE | 181,575 |
Instrumentation | 0.15 PCE | 60,525 |
Electrical | 0.1 PCE | 40,350 |
Building | 0.1 PCE | 40,350 |
Utilities | 0.375 PCE | 151,313 |
Storage | 0.2 PCE | 80,700 |
Site development | 0.05 PCE | 20,175 |
Ancillary buildings | 0.225 PCE | 90,787.5 |
PPC (A) (physical plant cost) | 1,250,850 | |
Fees of contractor | “0.050 PPC” | 62,542.5 |
Engineering & design | “0.250 PPC” | 312,713 |
“Contingency” | “0.10 PPC” | 125,085 |
(B) | 500,340 | |
FCI (fixed capital cost) | 1751,190 | |
TCI (total capital cost) | 2,188,988 |