Skip to main content

Table 1 The order of value engineering steps

From: Evaluation of influential value engineering factors on the function of interchanges: case studies in Iran

Pre-workshop steps

VE workshop steps

After-workshop steps

Project coordination

Information

Final report

Information preparation

Function analysis

Implementation

Preparation of models

Creation

Follow-up

Team members (1 to 3 persons)

Evaluation

Team members (1 to 3 persons)

Working days (2 to 5 days)

Development

Working days (2 to 5 days)

 

Presentation

 
 

Team members (5 to 12 persons)

 
 

Working days (1 to 5 days)