Name and location of the interchange | Base plan’s construction cost (IRR)* | Value plan’s construction cost (IRR)* | Base plan’s total cost (IRR)* | Value plan’s total cost (IRR)* |
---|---|---|---|---|
Khawrazmi (karaj) | 186,612,437,500 | 120,859,360,000 | 186,612,437,500 | 120,859,360,000 |
Rezvan-rahmat (shiraz) | 133,000,000,000 | 118,000,000,000 | 256,300,000,000 | 138,700,000,000 |
Chamran-Jalal Al-e-Ahmad (Tehran) | 256,606,000,000 | 293,717,000,000 | 614,377,000,000 | 352,460,000,000 |
Shahed-jadeh ghouchan (mashhad) | 245,502,000,000 | 148,084,760,000 | 245,502,000,000 | 148,084,760,000 |
Simon Bolivar-Yadegar-e-Emam (Tehran) | 512,185,000,000 | 677,449,000,000 | 3,445,590,000,000 | 2,155,609,000,000 |
Sepah Square (karaj) | 261,554,898,000 | 140,882,794,360 | 375,383,589,610 | 202,194,986,465 |
Jomhouri Square (karaj) | 50,324,296,000 | 23,552,210,000 | 72,225,429,629 | 33,802,131,792 |
Rezvan-koneh bist (mashhad) | 225,000,000,000 | 135,000,000,000 | 346,000,000,000 | 135,000,000,000 |