Table 7 Status of RM implementation: project level

From: Project risk management in Iranian small construction firms

Project characteristics

 

No. of projects

No. of projects with RM

% of projects with RM

Type

Public

19

6

31.5

 

Private

21

7

33.3

Nature

New Con.

21

8

38.1

 

RMAA

19

5

26.3

Cost (Rials)

< 4 billion

10

1

10

 

4–40 billion

22

8

36.4

 

> 40 billion

8

4

50

Duration

< 6 months

11

1

9.1

 

6–14 months

14

8

57.1

 

> 14 months

15

4

26.6

Total

 

40

13

32.5